1. Prepare the data room
Permit and prescriptions, grid connection solution, detailed design (layout, sections, single-line diagrams), geological and geotechnical reports, surveys, site rights, constraints and monitoring plans. For RTB projects most of it is usually ready.
2. Write a clear request for proposal
- Scope and what stays with the owner.
- Equipment: required or allowed brands, or minimum specs.
- Timeline: target start and COD.
- Guarantees and bonds required.
- Offer template with the same items for all.
- Draft contract or key terms. See EPC contract.
3. Invite few, but the right EPCs
Too many bidders slow everything and lower quality: the best EPCs skip crowded tenders. Better a few consistent contractors by technology, size and region. That is exactly what we do: see how it works.
4. Compare on the same basis
| Compare | Why |
|---|---|
| Price at equal scope | Exclusions shift cost to you |
| Equipment and warranties | Drive yield and long-term risk |
| Schedule and LDs | Delay costs more than a few euros per kW |
| Performance guarantees | Show how much the EPC trusts its design |
| Strength and references | An EPC in distress mid-site is the worst risk |
Send us your plant details
A few details are enough to understand which EPCs make sense for your case. We call you back; if you prefer, write to us on WhatsApp or call toll-free 800 955358 from Italy.
Frequently asked questions
What does a solar EPC cost per MW in Italy?
It depends on technology, size, site, grid works and market timing; averages found online say little about a specific project. The only reliable number comes from comparable offers on your project.