1. Scope and exclusions
The most important and most neglected part. The contract must state exactly what is included – detailed design, supply, construction, civil works, substations, grid works, security and monitoring, permits, testing, as-built documentation – and list exclusions. Anything unwritten risks becoming a paid variation.
2. Price and payments
- Lump sum or remeasured, with any adjustment clauses (e.g. module prices).
- Milestone payments tied to verifiable events.
- Advance covered by a bond and retention until final acceptance.
3. Schedule and delay damages
Key dates (start, mechanical completion, grid connection, COD) and delay liquidated damages proportionate to real loss, with a cap. With an external deadline such as a FER X or MACSE award or a PPA, LDs must match your exposure.
4. Performance guarantees
For solar, typically a performance ratio or yield guarantee tested after COD; for BESS, capacity, efficiency and availability. If values are missed, the EPC must fix or pay performance LDs.
5. Bonds and insurance
Advance payment bond, performance bond, warranty bond; CAR and third-party liability insurance. Amount, duration and issuer all matter.
6. Acceptance
Provisional (PAC) and final (FAC) acceptance with tests defined upfront, punch list and closing times, clear transfer of risk and custody.
FIDIC and Italian law
International investors often use FIDIC models, especially the Silver Book for turnkey works. They can be adapted to Italian law; what matters is an EPC able to work at that level of formality. See turnkey EPC.
Send us your plant details
A few details are enough to understand which EPCs make sense for your case. We call you back; if you prefer, write to us on WhatsApp or call toll-free 800 955358 from Italy.
Frequently asked questions
Do you draft the contract?
No: contracts must be drafted or reviewed by lawyers. We help compare offers and understand differences between EPC proposals.